Co-Op Park Los Alamos The Co-Op Park was funded by the community and supported by six local cooperatives. Collaboration is the unique cooperative advantage.

The park offers live performances and private events, community garden,
outdoor youth education with Little Forest Playschool, and a place for youth to safely gather. The Co-Op Park is a gathering place in the wake of a pandemic that drove us apart.

Our 6 amazing Los Alamos Cooperatives celebrated a major milestone yesterday.  After two successful community campaigns,...
20/10/2024

Our 6 amazing Los Alamos Cooperatives celebrated a major milestone yesterday. After two successful community campaigns, we were able to deliver on our promise complete Phase 2. Thank you to our generous members, community and volunteers for making this possible!

Ribbon Cut On Phase 2 Of Los Alamos Coop Park
https://ladailypost.com/ribbon-cut-on-phase-2-of-los-alamos-coop-park/

Week 9 Update- The construction is nearly complete. Gutters and lighting remain. In the coming weeks we will be working ...
19/07/2024

Week 9 Update- The construction is nearly complete. Gutters and lighting remain. In the coming weeks we will be working on setting up the audio components.

Week 8 Update- The wood soffit and roof edging was completed this week. Almost finished!
07/07/2024

Week 8 Update- The wood soffit and roof edging was completed this week. Almost finished!

29/06/2024
Week 7 Update- Last week we were waiting on electric inspection and now that we have the green light, the crew is back a...
29/06/2024

Week 7 Update- Last week we were waiting on electric inspection and now that we have the green light, the crew is back at it. The roofing and under eave materials are being installed.

Week 5 Update- Some electric conduit run this week and install of our equipment closet
10/06/2024

Week 5 Update- Some electric conduit run this week and install of our equipment closet

31/05/2024
Week 4 Update- Roof and membrane installed, sanding beams and prepping for electric next week
31/05/2024

Week 4 Update- Roof and membrane installed, sanding beams and prepping for electric next week

Week 3 Update- Major progress going vertical, brackets welded and beams fastened. Jim and crew’s hard work can now be se...
23/05/2024

Week 3 Update- Major progress going vertical, brackets welded and beams fastened. Jim and crew’s hard work can now be seen from the road. The scale is impressive!

17/05/2024
Week 2 Update- it was a rainy week but that didn’t stop the hard working crew from completing the concrete and test fitt...
17/05/2024

Week 2 Update- it was a rainy week but that didn’t stop the hard working crew from completing the concrete and test fitting the base brackets.

Week 1 Update- Fencing setup, holes dug, and two rear footers were poured. Josh working hard on the final touches 😉
14/05/2024

Week 1 Update- Fencing setup, holes dug, and two rear footers were poured. Josh working hard on the final touches 😉

Exciting news, Phase 2 construction has started! We are excited to have the canopy complete with lighting and sound for ...
09/05/2024

Exciting news, Phase 2 construction has started! We are excited to have the canopy complete with lighting and sound for future events/performances.

The Little Forest Playschool, Inc. group doing amazing work at the garden!
27/05/2023

The Little Forest Playschool, Inc. group doing amazing work at the garden!

27/04/2023
We need your help!  Our committee is actively looking for a local builder to construct our stage canopy. If you or someo...
18/01/2023

We need your help! Our committee is actively looking for a local builder to construct our stage canopy. If you or someone you know is interested in a winter/spring project please contact us immediately.

Snowy scene at the Co-Op Park!
18/01/2023

Snowy scene at the Co-Op Park!

26/10/2022

Oct. 25 Council news: Proclamation Declaring the Month of October as Co-Operative Month. Accepting the Proclamation from Councilor David Izraelevitz are (left to right) Josh Stringer representing the Del Norte LOV Foundation and the Del Norte Credit Union, Terra Hite representing the Board of Directors for the Los Alamos Cooperative Market, and Bethany Hayward representing the Los Alamos Schools Credit Union.

Address

NM

Alerts

Be the first to know and let us send you an email when Co-Op Park Los Alamos posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Co-Op Park Los Alamos:

Videos

Shortcuts

  • Address
  • Telephone
  • Alerts
  • Contact The Business
  • Videos
  • Claim ownership or report listing
  • Want your business to be the top-listed Event Planning Service?

Share